Required Documents for a Building Permit Application
Before submitting your building application, please ensure you have the following documents ready. Missing or incomplete documentation may delay the review process.
General Requirements
Completed Building Application Form
Copy of Notary Deed
Copy of Certificate of Admeasurement
Blueprint Drawings
All drawings must be in A3 format, at 1:100 scale, with legend:
4 Elevations (Front, Back, Left, and Right) – 2 copies each
Floor Plans (Ground and First Floor) – 2 copies each
Roof Plan – 2 copies
Electrical Plan – 2 copies
Foundation Plan, including septic tank, and piping – 2 copies
2 Cross Sections based on project complexity – 2 copies
Reinforced Plans with structural details (Foundation, Floor, Columns, Ring Beam, and Roof) – 2 copies
Layout/Situation Drawing – 2 copies